From: route@monster.com
Sent: Friday, August 19, 2016 10:44 AM
To: hg@apeironinc.com
Subject: Please review this candidate for: Project Coordinator KY
This resume has been forwarded to
you at the request of Monster User xapeix03
|
|||||||
|
|||||||
|
|
|
||||||
|
||||||
|
Robert Dabe Jr. 812-893-1832
rsd12453@gmail.com Skills
Machine Guarding Systems
Software
Testing Equipment
PROFESSIONAL EXPERIENCE Alcoa Warrick Power Plant - Consultant11/2015-2/29/2016
I was responsible for the 138kV and
15kV switchyards, along with UPS systems and fly ash precipitators. During
this time there was a switch failures, in each yard. I supervised the crews
making the repairs. In January, Alcoa announced the closing of their smelter.
I was asked to stay on due to a hiring freeze, and to complete the
installation and startup of a new precipitator rapping control system, and
replacement of damaged heat trace. MAI Engineering - Senior Electrical and Instrument
Coordinator1/2014-9/2015 I was responsible for all
electrical design within the company. The majority of the work was primarily
on systems located in petrochemical, paper, and chemical plants. I conducted
meetings to help them define the desired results. I created a draft scope of
work, and a detailed schedule. Obtained quotes for new equipment, and
estimated the total installed cost. I met with the client for a review of
what would be delivered, and identify any changes to the scope of work
needed. Using AutoCAD, Excel, and MS Word, I designed power and control
circuitry, created single line drawings, loop sheets, instrument indexes,
modified P&ID’s, and specifications for power circuits, transformers,
control instruments, control loops, and conducted site investigations, needed
to support my designs. Alcoa Warrick Power Plant - Consultant8/2012-12/2013 I had several major tasks I’ve
performed in this capacity. I took care of electrostatic precipitator
troubleshooting and repairs during generator outages. I was responsible
for creating electrical and mechanical scopes of work, and supervised
repairs. Worked with electrical contractors to “chase down” old wiring, then
generated AutoCAD drawings aid in future troubleshooting. Completed the full
replacement of all plant revenue meters. Was responsible for creating a
complex spreadsheet to graphically illustrate performance of operations
crews, and another to automatically extract NERC/FERC protective relay
calibrations. I also provided training for a new electrical engineer who had
been assigned all of my previous duties. Alcoa Warrick Power Plant - Electrical Project Engineer2005
– 2012 Electrical lead for a $550MM
project to add environmental scrubbers to all four of the generating units at
the power plant. Responsibilities were design review to assure all of Alcoa’s
requirements were supported, in addition to those required by the power
plant. I was the project SPA for machine guarding. I facilitated the use of
additional subject matter experts to assist with detailed design and
equipment selection for a new 138kV switchyard and modifications to an
existing switchyard, new 138kV 40 mVA power transformers, new 13.8kV and
4160V power distribution building, unit substations, 4160 and 480V motor
control centers, process control systems – Foxboro DCS and Allen Bradley
PLC’s, CEMS systems, UPS systems, extension of existing plant networks, fire
systems, and phones. Coordinated construction work to eliminate any impact to
plant operations and maintenance. Attended all factory acceptance tests for
new equipment, machinery, and control systems. Worked with the EPCM (Fluor
Global) startup and commissioning teams, to assure systems worked as
designed. Assigned to the Technical Services Department, as an electrical reliability
engineer to improving the reliability of plant electrical and control
systems. Responsible for plant electrical projects, and was the SPA for
electrostatic precipitators and all UPS, and revenue metering systems.
Assigned the position of Pre-Production Reliability Activities (PPRA)
coordinator. PPRA is a process that looks at every part on every piece of
equipment purchased for a project. It then quantifies the critically of a
part, then looks at the lead time to purchase it, its cost, and quantity
being installed. From this recommendations are made that identify the actual
number of spare parts that need to be stored onsite. This process typically
saves twice the amount of its cost, in spare parts not ordered. Alcoa Mill Products - Electrical Project Engineer (note: in 1998 Alumax merged with
Alcoa)1995 – 2005 Assigned many projects in the cast
house, stress relieving, milling, inspection, and packing departments. These
included combustion upgrades, automated plate stacking robots, revamp of many
machine control systems, and installation of a plant wide data collection
system. Provided detailed design for many projects, after working with
production employees to assure their needs were met. Responsible for all
electrical projects accomplished within the plate facility and served as
backup for the maintenance manager. Responsible for the maintenance and
repair of all electronic devices and computers at the plant, including
spectrometers. Worked extensively with contractors from differing disciplines
to accomplish the projects I was assigned. Developed scopes of work and
assured contractors comply with them. Loaned to Yunan Xinmeilu Aluminum Foil
Co., a joint venture between Alumax and an aluminum foil mill in Kunming,
China. I supervised the commissioning of a casting line, bag house, two scrap
bailers, an intermediate foil mill, and a foil separator. Served as plant
scrap Manager. Plate is a single alloy plant runs on 100 percent scrap. I was
responsible for the control of all scrap aluminum and hardeners. I developed
a spreadsheet program for scrap aluminum. Project Manager for Plate Y2K
compliance. Was responsible to insure the smooth transition through testing,
remediation and documentation of all plant devices including hardware and software
for PC’s, PLC’s, and other devices with embedded processors. Stockroom
Manager – I was charged with the complete organization of the Plate Facility
stockroom from a non-existent system to one that was fully computerized for
control of stockroom inventory. Alumax Mill Products - Senior Engineer1994 –
1996 Involved with the re-commissioning
of leveling and slitting lines, relocated from the Riverside plant, to its
Texarkana plant. Promoted to senior electrical engineer. My first task was to
work with a company in Bath, PA who was in the process of developing a
prototype device to measure the thickness and profile of a finished cast
aluminum plate. Once completed, it was shipped to California, where I
installed and commissioned it. Worked with Raytheon Engineering to design and
build a green field plant in Lancaster, PA. My primary purpose was to assure
Raytheon met all of the electrical design criteria, expected by Alumax. The
facility would eventually receive all of the plate department machinery in
Riverside, along with a new plate caster and horizontal plate mill. During
the construction period I worked with the construction company, to assure all
of the electrical power systems were installed and commissioned properly. In
addition I contracted a controls company to convert all of the older control
systems from hard wired relays and pushbuttons to PLC based control with
touch screens. I was directly responsible for startup and commissioning of
those systems. By the end of 1995 the plant construction was complete. Enough
equipment had been commissioned was operational in January to start up the
plant. Alumax Mill Products - Electrical Lead man1987
– 1994 Troubleshot and repaired printed
circuit boards to the level, repaired SCR packs, worked on the plant
quantometers, installed and commissioned the first data collection system on
a sheet caster, and modified the program extensively, to fit our needs. Once
that was complete I wrote programs on a remote PC to collect the data. Alumax Mill Products - Industrial Electrician1978
– 1987 Troubleshot and repaired of reverb
melting and holding furnaces, continuous sheet and plate casters, cold mills,
shape control systems, annealing ovens, levelers, paint lines, slitters,
horizontal plate mills, roll grinders, AC & DC drives, PLC’s, and all
other plant equipment related to the support of the manufacturing mission.
Designed, constructed, wired, and tested numerous control panels. Electrical construction work
associated with the installation of a new plate caster, installation of a new
annealing furnace, relocation of a sheet caster. (Electrical lead), the
installation of a new slitter (Electrical lead), and the installation of a
new paint line. US Air Force - Facilities Electrician1971
– 1979 Served as a base facilities
electrician where I progressed from a basic to journeyman electrician. Education US Air Force - During my eight
years of service, I was required to advance my electrical knowledge through
technical training. In addition to those courses I completed advanced courses
which included military grade intrusion and fire protection systems, HVAC
controls, and cathodic protection systems. Anaheim High School, Anaheim
California, Riverside Community College, Riverside California - Core
curriculum and electronics courses. Valley College, San Bernardino California
- Math and programming courses. |
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Languages: |
Languages |
Proficiency Level |
|
English |
Fluent |
|
|
|